12-11-2008 11:04 AM
hello,
After creation of an adjustment reversal I rebill the contract. In case that I didn't make any change in reading, I am getting blank lines in FPL9. Is there any cust. in order not to create blank lines in case of adj. reversal?
Because I am using 'installation group', I am doing adjustment reversal without reading changes for all the group.
thanks,
ben
12-11-2008 12:15 PM
Hi:
You should try after changing the meter reading else try by t/code EA00.
Regards
Shashi