We are running tcode CJCO ,carry forward budget balance of 2008.Then system says on executing :
"update run only possible for closed fiscal years"
Pls let me know how to correct it.
Resolved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
InCJCO txn you can transfer a budget that was not consumed for a project within one fiscal year in to following fiscal year.
however committment are ignored when the budget values to be carried forward are calculated, you should have used a cmommitment carryforward intnx CJCF before you carry forward budgets.