Information on closed projects

Former Member
0 Kudos

Hi All,

I have two questions:

1. How can we check , on which particular date the project was closed.

2. Is there any way by which we can close n number of projects in one go without doing it individually for each and every project.

Regards,

Vishal

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

thanks all

Former Member
0 Kudos

thanks for your answer.

Former Member
0 Kudos

Hi,

For question 2 :

You can ask an Abaper to write a program by which it will track the projects in your system and can close or change the status of those to TECO or CLSD (anyone u want) .

Thanks ,

Dhruv Kumar Malhotra

Former Member
0 Kudos

Thanks .........

nitin_patoliya
Active Contributor
0 Kudos

For Q1

Go to Cj20n --> click on the WBS / netwrok activity (for which you want to see the status change track.) --> Edit menu > Status> system/ user status ( system will take you to change status screen ) --> go to extra menu --> change document --> all ( system will take you to change docuemnts in status management ) use 'all changes' & 'history' tabes for your analysis.

For Q2

For the mass changes in PS there is Txn CNMASS but in that you cannot change the status of project. How ever simple work around is ask your ABAPer to write BDC.

Regards

Nitin

Former Member
0 Kudos

1. How can we check , on which particular date the project was closed.

Go to Cj20n --> click on the Project/WBS / netwrok activity (for which you want to see the status change track.) --> Edit menu > Status> system/ user status ( system will take you to change status screen ) --> go to extra menu --> change document --> all ( system will take you to change docuemnts in status management ) use 'all changes' & 'history' tabes for your analysis.

2. Is there any way by which we can close n number of projects in one go without doing it individually for each and every project.

I think it may not be possible.

Venkat