Hello All,
I have a requirement where I need to assign Profit Center of Project definition to WBS element 1 down to the activity level and the structure so that all have common profit centres.
For WBS I can handle it seperately by Validation. However I am not sure how to populate the same Profit Centre to Network header and Activity level.
Looking to use some standard BAdI or User Exits. Please guide.
Thanks
Sarang
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Nitin and Venkat.
Nitin - But how do we populate the Profit Centre from Project Defn to the Network Headers for all Network ?. Once we have done this then we can use substitution to cascade the same down to Activity level. But the main problem is populating same PC at Network header levek.
Venkat - The link gives information on PS tables and BAPIs and not BAdI.However that is useful too.
Thanks
Sarang
You can do the similar validation rule for the network header & activity. The you ahve to maintain in network profile (OPUU) & that network pfile you have to assign to your project profile.
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.