Hi All,

cost planning profile - Overall cost planning.

planning Element selected , Bottom up planning selected

CJ40

Ex. WBS Element Manual Cost Plan Total Planned Costing Network Order

XYZ 6000 8700

XYZ -1 1000 2100 500 600

XYZ - 2 5000 6600 1000 600

But In Report

S_ALR_87013533

WBS Element Plan Overall Actual Overall

XYZ 7500

XYZ -1 1500 (Manual + Costing)

ACT10 300

ACT 20 300

XYZ - 2 6000 (Manual +costing )

ACT10 300

ACT 20 300

actual total planned cost to 8700 ( activity cost it is not considering)

Please do Suggest.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi, Tick the check box 'Integrated Planning" in control tab in the project definition. Then run CJ9Q. Trust this helps much! Cheers!