on 12-09-2008 1:52 PM
Hi All,
cost planning profile - Overall cost planning.
planning Element selected , Bottom up planning selected
CJ40
Ex. WBS Element Manual Cost Plan Total Planned Costing Network Order
XYZ 6000 8700
XYZ -1 1000 2100 500 600
XYZ - 2 5000 6600 1000 600
But In Report
S_ALR_87013533
WBS Element Plan Overall Actual Overall
XYZ 7500
XYZ -1 1500 (Manual + Costing)
ACT10 300
ACT 20 300
XYZ - 2 6000 (Manual +costing )
ACT10 300
ACT 20 300
actual total planned cost to 8700 ( activity cost it is not considering)
Please do Suggest.
Hi, Tick the check box 'Integrated Planning" in control tab in the project definition. Then run CJ9Q. Trust this helps much! Cheers!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.