Materials for Single wbs Element from project/Plant stock

Former Member
0 Kudos

Hi to all,

I would like to have the following scenarios for the single Project.

1) Some Activities in the single WBS Element will be using the Materials for specific to the Project. So MRP will be generated for the Project and PR,PO,Goods receipt will be done.

2) In the same WBS Element of some activity, wants to consume materials from the Plant stock. For this we donu2019t want to run MRP. From the reservation no, we want to take the materials for project use.

I have a single Network profile and I donu2019t want to create anymore.

Understand from movement type 411, we can take the materials from unrestricted Plant stock to project. Is there any other way/any config I need to check in account assignment category to fulfill the requirement to consume from Plant stock and also to use Project stock in a single profile.

Regards

N.Raju

Accepted Solutions (0)

Answers (1)

Answers (1)

venkatesh_kulkarni1
Active Participant
0 Kudos

Hi,

that is the only option, Std. SAP does not support for unrestricted plant stock ( for Project MRP or availability check).

same option-

1) transfer free stock( plant stock) to respective WBSE

2) Run MRP

3) Consume material.