bom explosion problem

Former Member
0 Kudos

Hi all,

In md4c transaction bom will not be exploded for multi level order report.

ex;Header(DU) level procurement proposal is displayed,Not exploded for assembly(component )

This is very very critical.

Please guide me how to do it.

Thanks

Sukumar

Accepted Solutions (0)

Answers (1)

Answers (1)

ansar_shaikh2
Contributor
0 Kudos

Exploding the BOM

If you have allocated a material with a bill of material (BOM), a sales order BOM, or a WBS BOM to an activity, you can explode this BOM in the network level-by-level or completely (multi-level).

If the material component was already allocated to the activity before the BOM explosion, you have the following options.

u2022 You select the component and proceed as below. When you do this, the "header" material is assigned the item category T (text item) which means that no requirements will be generated for it, just for the subordinate items.

u2022 If you do not select the component, but enter it manually in the dialog box, it remains allocated to the network with the original item category. You can delete this component or define it as an assembly item, by giving it a negative requirements quantity.

Procedure

1.On the Component Overview screen for an activity, choose Components

Explode BOM.

The BOM selection dialog box appears.

2.Enter the necessary data, for example for a WBS BOM the WBS element for which the BOM was created. The default value for the requirements quantity is the

Execution Factor in the activity. You can explode the BOM level-by-level or all at once (multi-level).

If you explode the BOM all at once, requirements could be generated both in the network and in MRP, depending on control of the BOM items. Since MRP always explodes the complete BOM, this could lead to multiple requirements for the same component.

3.Choose Continue.

A list of all the BOM items appears.

Document items are not includes in this list, since the system does not copy document items to network activities.

4.Select the items that you want to allocate to the network and choose Copy.

5.If necessary, check the data for inventory management and account assignment.

6.Save the network.

Hope u will understand the process

Regards,

ANSAR