Hi Gurus
I'm very new to cProjects and SAP PS.
When we created a Project in cProejcts we assign an Organization Unit Responsible which has a Profit Center of e.g. 12345.
For each WBS Element associated with the Project they will have a Profit Center which does not match the Project Profit Center.
Yet when we run Settlements all of the WBS Elements are reflecting against the Project Proft Center, not the individual WBS Element Profit Centers.
Would someone be able to point me in the correct direction as to how I can configure this such that the correct Profit Center is updated when I run settlements.
Many Thanks in advance
Panduranga
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Panduranga,
Please check whether you are using Single Level or Multilevel Controliing for the particular project type.
To settle the cost to the respective WBS profit center, you should select Multilevel Controlling for the project type.
Regards
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.