proj materials

Former Member
0 Kudos

we are planning materials on the project thru reservations the movement type is 221 consumption to proj... what are the reports availble for the same for tracking material....

for planning i use MB25

for actula posting i am using cj13 : actual cost line items...

any other ??

Accepted Solutions (0)

Answers (3)

Answers (3)

nitin_patoliya
Active Contributor
0 Kudos

Requirement / Stock (MD04 😞 It dispalys the stock situation of material, as well as requirements and planned activities in the different stock segments.

Valuated project stock (MBBS)

you canuse this report to evaluate materail that is managed in valuated project or sales order stocks.

Missing parts ( Co24)

To evaluate material componets that were identified as missing parts within the availability check.

Pegged requirement ( MD09 )

For multilevel production processes to determine origional pegged req. for selected orders.

Order report ( MD4c)

To moniter the possible multilevel production of materail for projects.

Individual Overview (CN52 / CN52N ) Ps information syst to evaluate data for materail in networks or assgned orders

CN44 /Cn44N & Cn45/ Cn45n To evaluate planned and production orders for Projects.

Regards

Nitin

Former Member
0 Kudos

U can check even Proman, Tcode:CNMM.

Venkat

Former Member
0 Kudos

Hi,

Reports like CN52 & MD4C could be useful.

Murali