Production order should be confirmed before in-process inspection UD

former_member1005887
Participant
0 Kudos

We guys,

I have activated the In-process inspection for one Finished goods and inspection lot is getting created when Production order released. This production order can be confirmed without UD for In-process inspection lot.

Please let know How can I control that Production order should not be able confirm before UD of Inspection lot for in-process inspection.

When production order released it means an production has just starded. Then What is the meaning in getting the inspection lot created on release of production. I think it is supposed to be on completion of each opration.

Please give your inputs.

Thanks

Dhanu

Accepted Solutions (1)

Accepted Solutions (1)

former_member186399
Active Contributor
0 Kudos

Hello,

This can be done in 2 ways

1) In configuration for Production order OPK4 you can make sequence mandatory. Ideal config is

1) Operation sequence - Error when operation sequence is not adhered

eg So if you operation of QM 0030 , 0040 can be confirmed only after 0030

2) Over delivery - Error when overdelivery tolerance is exceeded.

eg - 0030 operation 2 quantity is confirmed then in 0040 you cannot confirm more than 2

3) Result Rec QM- Error message If no inspection results exists

2) use user exit for the same confpp05

Please revert back

Regards

Gajesh

Answers (1)

Answers (1)

former_member186399
Active Contributor
0 Kudos

Hello

inprocess inspection are used to assisst you to record results , defect , rework, during the production operation. It is defined to get created during the release of the order. It gives QM personnel a control over the quantity confirmation. You can do the result recording based on time and quantity.

Operation confirmation and UD are independent and it will not be possible to do confirmation once you do the UD.

The controls that can be brought in 03 inspection for a better usage

1) Result recording mandatory for all inspection points

2) QM operation can be confirmed only by QM personnel

3) At the time of GR of the order check whether UD for the lot is given. Make UD mandatory for GR of the order

4) Only after QM operation confirmation the next operation can be confirmed

5) make use of Rework to capture rework cost and First Pass Yield

Hope this gives some picture to you

Regards

gajesh

former_member1005887
Participant
0 Kudos

4) Only after QM operation confirmation the next operation can be confirmed

Can you please brief me about above point which will suite my requirement