Can Milestone trigger down payment request?

Former Member
0 Kudos

Dear all,

could you help me on this issue?

i am working on the PS project for sales.

During the long-time process, we will receive three down payments.

Can the down payment request be triggered by the milestone?

does it have to intergrate with SD or WBS billing plan or milestone billing can do it?

we need to see the down payment amount in the PS report.

Please tell me some detailed information. thanks a lot.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Down payment can be triggered using planned using milestone. Milestone usage determines whether it is a down payment or partial payment. In IDES it is PS04 for Down Payment. Usage is assigned while creating a Milestone.

Use CJIA report to see the down payment.

Also refer below link....to get more insight in Milestone Billing

http://help.sap.com/saphelp_470/helpdata/en/dd/5606b5545a11d1a7020000e829fd11/frameset.htm

Venkat