Dear LE Friends,

Tme between the material availability date and transportation date should be 2 days.

Where do we make settings for the above requirement. I think it can be in the route or shipping point, but i am not sure.Can you please guide me.

Regards,

Sampath

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You can maintain in pick/pack time and loading time in shipping point definition

-Sudheer

Former Member
0 Kudos

Hi,

Additionally, you have also option to define transportation lead time at route definition.

But from what I understood it is more related to warehouse operations, and thus I agree this to be more pick/pack/loading timing at shipping point.