on 12-05-2008 5:13 PM
HI,
I'm restructuring the project by moving released NWA from one WBS to another to aling actual costs with new budget categories.
After moving these NWA I run the report and found out that WBS element summarize costs even if there is no NWA under this specific WBS.
What field should I enable to allow WBS elements recalculate costs according to new NWA under these WBS.
Thanks,
Minsk2000
Hi,
Run CJEN to reconstruct project database.
Rgds
Abhinay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.