Moving NWA from one WBS to another and consolidated costs under WBS

Former Member
0 Kudos

HI,

I'm restructuring the project by moving released NWA from one WBS to another to aling actual costs with new budget categories.

After moving these NWA I run the report and found out that WBS element summarize costs even if there is no NWA under this specific WBS.

What field should I enable to allow WBS elements recalculate costs according to new NWA under these WBS.

Thanks,

Minsk2000

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member214674
Contributor
0 Kudos

Hi,

Run CJEN to reconstruct project database.

Rgds

Abhinay

Former Member
0 Kudos

Could you please clarify what should I do in CJEN

former_member214674
Contributor
0 Kudos

T code : CJEN

Enter Project Defination

Uncheck "Test" Check box

Execute.

Rgds

Abhinay

Former Member
0 Kudos

Thanks tons Abhinay

Have a great weekend!