Dear all!

It´s about the scale of the DP-Graphic. I already asked in SAP-Training but could not get a sufficient answer.

In the planning-book definition my past-horizon is 30months and my future-horizon is 18months.

I want that the time series in the graphic is the same range like the table (-30 to +18 months)!

There should be an automatic shift from months in the graphic eg:

Nov08: May2006 - Apr2010

Dec08: Jun2006 - May2010

Jan09: Jul2006 - Jun2010

When I set everything to automatic in Format Axis --> Scale

it always beginns with 1970!

Thanks a lot...

Martin

Accepted Solutions (1)

Accepted Solutions (1)

samir_ali
Participant
0 Kudos

Hi Martin,

are you still lookinf for ans.

If yes then I would like to know which SCM ver. are you using it ?

1) If you you are using SCM 5.0 & For Support pack 12, then apply SAP note 1225137

2) Apply SAP note 931009 for

Support Packages

SCM 400 SAPKY40019

SCM 410 SAPKY41011

SCM 500 SAPKY50004

Hope this will solve your issue.

points are welcome

Regards

Samir