Hi everyone
In enterprise structure, I have my Sales Org 1350 assigned to Company Code (CC) 1350 while Sales Org 1300 to CC 1300. And then Plant 1352 is assigned to CC 1350 and Plant 1302 to CC 1300
Now when I create a Sales Order with sales org 1300, it shud pick plant 1300 right? It picks 1352. How? Surprisingly that's how it shud be, maybe some config they've done which I am not aware of. Any ideas?
Now my problem is when I do PGI with a sales org 1300 Delivery. It says GL account 132055 not defined for CC 1350
Now I see 132055 is defined for CC 1300 but not 1350. Do I need to define GL account for 1350 or there is a way around to make it CC 1300?
Hi vik luthra
Fir your first query , go to shipping point to plant (OVXC) and delete the plant 1302 and assign only plant 1352 which has been assigned to your shipping point for the enterprise structure of sales orgn 1350 c.code 1350 .and go to OVL2 and assign the shipping point as per your data maintainence
For your second query , if your doing normal cycle then how can you do PGI with sales orgn 1350 which is not assigned to Company code 1350 .Check properly the assignment of sales orgn to company code.
Regards
Srinath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sri Nath
Really appreciate your help. The first query is clear.
For the second, I think you meant 1300 is not assigned to CC 1350.
So when I create an order with Sales Org. 1300, it picks plant as 1352 (which is correct). Now on PGI, it complains about GL account missing in CC 1350 (b'coz Plant 1352 is assigned to CC 1350. I think the solution would be to assign that GL account for CC 1350).
Please let me know your thoughts.
Regards,
Vik
Hi vik
Ya , as per your query , you were telling that sales orgn 1300 is assigned to C.code 1300 (and another enterprise structure is sales orgn is 1350 and c.code is 1350) only but you were telling that a sales order has been created and when you were doing PGI it is giving error sales orgn 1350 to co.code 1300
Go to FS00 and check wheather that G/L account is there or not in that 1300 company code
Secondly check in OVX3 Company code -> Sales organization , here you check wheather the assignment has been done or not
Regards
Srinath
Dear Vik,
Just check with the Material Master, as entred in to Sales Order.
In T. Code: MM02,
Check, whether material is being created/ maintained with the Plant 1352, Sales Org. 1350 & Dist. Channel.
It might, possible that material is created with Plant 1302, instead of Plant 1352.
Best Regards,
Amit
Note: Other areas to check:
1. CMR (XD02) - Check with Customer Master (being used in Sales Order). In Tab: Sales Area Data --> Sub-Tab: Shipping
What "Delivery Plant" is maintained there?
2. Check, whether any CMIR (VD52/53) is being maintained? If yes, check with Plant assignement in that.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.