Factory calender for cost activity in Standard network

Former Member
0 Kudos

I have problem to specify factory calender for a primary cost activity in a Standard Network (CN01,CN02).

It is only possible to do it for internal processing.

Do you know where the factory calender comes from when you copy the Standard network into a project?

It is not the same as the calender in the standard WBS or in the running WBS.

It is not the same as in the project profile.

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

the factory calendar for the cost activity is derived from the plant on the cost activity

if you are trying again do recreate the activity or change the plant and then change it back to refresh the data on the template

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

The factory calender for the "general cost activity" comes from the "plant" assigned to it !

The priority is for that only,superceding the plants present in project profile, project definition, and the WBS elem ( standard & operative) ...all of these .

hope that answers the question !

Best regards,

M.Amarendra