Hi Experts,
I am trying to transfer material bom components to network activities, but the components are not getting attched and i am not able to see those componets in the netwrok activities.
what i did.
1- Created one ref point
2-Entered the same ref point in BOM component
3-Created one activity and attached the same ref point in that activty and saved.
After this i feel , all the respected componets should get attached to the activity,
but its not happening.
Can anybody put some light on this, where i am doing the mistake.
Regards
Ashis
Edited by: ashis mohanty on Dec 4, 2008 1:35 PM
Hi ,
After you have maintained the reference point for both BOM and the internal activity at the places where
they should be , you need to take care of the following fields in the transaction CN33 ( which basically helps to execute the assignment of BOM components to the Object in question ( network activity )
In CN33, you need to fill up of the following fields,apart from Project Def or WBS elem and Network
1.selection profile
2.Material name
3.BOM Usage ( this should match with what has been maintained in material BOM )
4.If alternative BOM is maintained, you need to fill this too.
and then execute..
Check the same..It should help !
BR,
M.Amarendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
After you have maintained the reference point for both BOM and the internal activity at the places where
they should be , you need to take care of the following fields in the transaction CN33 ( which basically helps to execute the assignment of BOM components to the Object in question ( network activity )
In CN33, you need to fill up of the following fields,apart from Project Def or WBS elem and Network
1.selection profile
2.Material name
3.BOM Usage ( this should match with what has been maintained in material BOM )
4.If alternative BOM is maintained, you need to fill this too.
and then execute..
Check the same..It should help !
BR,
M.Amarendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Prequisitue of BOM Transfer : The automatic assignment of BOM items to network activietues is performed via reference point field that you can find in the inter processed activeity on assignment tab & in BOM items in the Basic data details screen.
Use tan CN33 --> enter you project no. --> execute.
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
you need to run cn33 after you have specified reference points on both network activities and bom component
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.