on 12-04-2008 9:14 AM
Hi,
We are developing a report for showing the goods receipt date of project stock. ( Copy of MBBS with additional fields to display such GR date of material)
A material becomes a project stock upon goods receipt against a purchase order or goods receipt of a production order , both of which are account-assigned to a wbs.
Please advise which tables to use to get GR date for purchase order and GR date of production order, by giving material number , special procurement key , wbs number as input.
Thanks in advance,
Manohar
Hi
Try MSPR table ( this has got a "created date" field in it ) along with MSEG ( for GR values )
and PO values are in EKPO table and Production order values are in AUFK table
All 4 tables !!
hope this helps.
Best Regards,
M.Amarendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Try MSPR table ( this has got a "created date" field in it )
hope this helps.
Best Regards,
M.Amarendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
try MSEG with matnr as input
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.