on 12-03-2008 2:49 PM
Hi All,
We have created a project in PS.
While generating Purchase Requisition thru MRP in MD51, account assignment category (Q) is coming, but the account assignment tab is missing in the purchase requisition.
But when we are generating PR thru CJ20N with prelimnary requirement as a procurement indicator then the WBS is getting fetched in Account assignment tab.
Please assist urgently,
Thanks
Sanjay
Problem cracked.
It was due to MRP plant parameters not maintained in OPPQ.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As you have mentioned that when you are creating PR from CJ20n you are able to fetch WBS element in the account assignment tab.
But when you try to create with MD51 you are not able to find the account assignment tab.
Please check IMG settings MM--> Purchasing >PR> Define screen lay out at document level.
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.