on 12-02-2008 2:47 PM
Hi experts!
Has anyone tried to change the dates in demand planning when transfer to SNP?
I would like the following. When releasing the forecast for week 49-51 we would split it into daily buckets (no problems here). But if we have a forecast for 200 for week 49 and 1000 for week 50, we would like to have a daily forecast of 200 for thursday and friday week 49 ( all daily forecasts moved two days earlier). This is to compensate for transportation duration time for the ATP check in R3.
Dag
Hi,
You would be able to do that using the BADI /SAPAPO/SDP_RELDATA. You can include code in may be method CHANGE_DATA_BEFORE_SPLIT that look up the calendar and add the week 49 forecast and display in thursday and friday.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.