on 12-02-2008 12:37 PM
Dear all, please help.
Is it possible to reassign existing WBS element to new project definition?
Have you done that in a not standart way?
There are costs already collected on that WBS element.
Please suggest.
once costs are posted it is best to create a new WBS and settle all the costs from the old one
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have an idea of assigning WBS elements to new project definition in a not standart way.
I want to change project definition directly in PRPS (field PSPHI - current project definition) by ABAP program.
I think that will be a simple way of project restructuring in one step.
May such approach cause problems?