Dear PS gurus!
Want to know that can we create one project having multiple plant, if yes ? how we will do costing?How to customize?
plz let me know the concept.
Ansar
Project Defination is not cost object, if you want to use WBS element across the projects don't give any plant in the Basic data tab of project.
In the Project there will be WBS element based on requirement. Each WBS element can be assinged to required plant.
So, in the same project you can use WBS across plant & company code, for that no customisation is need to be done in PS.
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanx for all ur inputs
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
you can have multiple plants in one project
there is no customising for this - the plant would be set up as part of enterpise customising
the costing will be based on the WBS object assigned
for eg you can have a project where some work is carried out in plant A and some work in plant B - projects can be cross plant the cost will be assigned to the WBS based on the actual postings but the WBS can have different plant assignments
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.