on 12-02-2008 6:56 AM
Hi All,
I need to update Cost Centers and Profit Centers in existing Projects(CJ20N).
Actually when the Projects were created Cost Centers and Profit Centers were not given. Now the customer needs them to be given there.
Do let me know if there is any tool or method I can use for updating the same.
Also clarify whether it can be done through LSMW or not.
Regards,
Raj Kumar Reddy.
If you wish to do it manually, check the feasibility of using T Code CNMASS.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
can use LSMW - that is actually the best option
use CJ07 and CJ12 for project def and WBS respectively for your recording
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Raj,
Your ABAP team can write BDC. For BDC you have to record one record with Tcode SHDB.
As Nitin told It can be done through LSMW as well.
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can do it through BDC .Please consult your ABAP Person.
Regards,
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.