While doing final settlement for WBS , The following error message comes.

" Asset under construction is not completely credited."

Please suggest the solution .

Thanks in advance.

Regards,

Vishal

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

There could be following possibilities

1.There are no distribution rules with the settlement type FUL

2.The total percentages of the rules is greater than 100 %

3.Only amount rules were maintained

4.WBS status not TECO

Check note 198931 for details.