can any body help me in creating a dummy work center only for showing duration and work in internal activities.. my client does not want to plan or post costs thru it. i have done some work on the same.. but it still needed a cost center. do we have to create activity types if only want activities for tracking plan / actual work and scheduling the activity.
thanks,
rahul
You have asked too many thing, But Your primary question is " you don't want to plan or post cost throgh activities "
For solving the above you have to create control key via Txn OPSU in that dont select tick for the
Costing. ( reming other indicator you can select based on for which types of activities you want to use this control key )
If you even press F1 selecting each of the indicator you will get the idea...........
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.