Dear All,
Our client is in Metal Industry. All his orders are projectized inside PS, they have deliverables which for example is Material X. This material X is consisted of materials A B and C. Once A/B/C are manufactured X just be complete.
I tried used Strategy Group 21 (Make to Order / Project Settlement) and Special Procurement 52 (Collective Order) and placed a requirement inside the project system for Material X.
once I run MRP, it generated Ordersfor X/A/B/C. My problem is, after I finished any of A/B/C I want to deliver them to the project stock and have X complete. Special procurement 52 doesn't allow me to do any deliveries (GR) for A/B/C, only for X.
What's the best practise for this?
I was thinking of making a project WBS bom for material X and putting in it A/B/C but I don't know what impact this WBS BOM will do.
Please understand that in the project system the team only asks for X, they dont know that it is made from A/B/C until the technical department lists these structures (after looking at technical drawings)
Anyone?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.