Factory Calender and Time Stream

former_member328462
Participant
0 Kudos

Hi,

I Maintain a factory calender A

where monday to friday is working

and holiday on 1/1/2009

My Distribution centre is working 1/1/2009

How do i set up in APO?

thx

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Maintain Production calendar (For Factory) and Distribution calendar (For DC) using transaction

S_AP9_75000138 - Maintain Planning Calendar (Time Stream)

In calculation rule maintain 5 days as working day using calculation rule "Weekdays"

then go to bucket delete day 1/1/2009 if showing as working day in Production calendar and keep this day as working for Dist calendar.

Then go to Location master in Calendar tab

assign Production calendar for factory location and distribution calendar (in shipping and recving) for DC.

Answers (0)