Dear All,

I am doing the STO (INTRA COMPANY) from plant 1 to Plant 2 for FG

While receiving the material in plant 2, I have to take as Semi finished good (SFG).

Is it possible? Bcz the Material Type is FG in Plant 1, so we can't change Valuation class of the Material while extending in Plant as SFG. How can I achieve this with same Material code?

While selling the same Material from Plant 2, I will add some part and I will it as a FG.

Please guide me.

Thanks & Regards,

Ramu

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Not solved

Former Member
0 Kudos

hai,

you can acheive this with tcode "MMAM" - but the stock must be zero in the receiving plant and inthe supplying plant, after that you can upload the material stock

regards,

Sudhir

Former Member
0 Kudos

Hi Sudhir,

Thanks for your reply.

But my requirement is in Plant the Material type should be FERT(FG) and while extending the same material in Plant 2, the Material Type sholud change to HALB(Semi finished).

As per ur answer I can change the Material Type for the Material in bith the Plants.

Plz guide me.

Thanks & Regards,