Hi experts,
Our client requires confirming activity based on sequence means current activity should not allow to confirm before predecessor activity confirmation. Is there such control in SAP PS activity confirmation?
Regards
Prasad
Hi
I do not think it is possible with Std. procedure. You may have to go for specific development.User exit EXIT_SAPLCORF_008 will be required in the process.
For details please refer SPROProject System-Confirmation--Enhancement for confirmation.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
$$
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
in that case do not release the suceeding activity
set a milestone on the preceeding activity with a function to REL the suceeding activity
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.