Possibility for Control the activity conformation based on sequence

Former Member
0 Kudos

Hi experts,

Our client requires confirming activity based on sequence means current activity should not allow to confirm before predecessor activity confirmation. Is there such control in SAP PS activity confirmation?

Regards

Prasad

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

I do not think it is possible with Std. procedure. You may have to go for specific development.User exit EXIT_SAPLCORF_008 will be required in the process.

For details please refer SPROProject System-Confirmation--Enhancement for confirmation.

Regards

Answers (2)

Answers (2)

Former Member
0 Kudos

$$

virendra_pal
Active Contributor
0 Kudos

in that case do not release the suceeding activity

set a milestone on the preceeding activity with a function to REL the suceeding activity