How to assign a personnel number (HR) to a PS activity

Former Member
0 Kudos

Hello,

I' ve created internal processing activities with allocation to a work center/ activity type for planning resources. Furthermore i'd like to detail a step deeper in allocating personnel number to my activity.

Can you please explain me how i can make appear personnel assignment tab in my activity?

Thanks in advance

Nathalie

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

U need to run capacity planning to see the person assignment tab. Please check the "Capacity Requirements" box in Network 'Schedule" tab using CJ20N. Then scheduling the project. U wud see the "Person assignement" tab for internal activity.

U can also use CMP2 or CMP3 to assign the resource to activity.

Venkat

Former Member
0 Kudos

thanks for the advices but it's not really working in my configuration. Is there any special customizing to foreseen in the work center to see the personnel assignment tab in the project?

Thanks in advance,

Nathalie

berit_eide
Explorer
0 Kudos

In your work-center you must make sure that the scheduling is set to person.

In the screen capacities, you will need a formula. I normally use SAP008.

In the same screeen, the capacity must be 002, person

In the capacities, you will then find the link to HRMS.

I hope this was helpful to you.

Regards,

Berit Eide

Former Member
0 Kudos

The person assignments tab will appear only if you have assigned the workcenter & allocated hours in the internal activity

Best Regards

Renjith