Hi Guys,
How do i check if all CATS entries have been transfered to PS for a particular Network & activity or WBS, I am trying to check with CATSDB table.
The procedure we have for CATS is
CAT2(enter time)-> Approve using CATS_APPR and transfer using CATA(background JOB).
Regards,
Paval.
As per process described by you I belive the entries should move in this way
Table CATSDB> CATSPS>AFRU or CATSDB>CATSCO>COBK.
You hvae to check your config setting for that.
For you help please go though attached link
http://help.sap.com/printdocu/core/Print46c/en/data/pdf/CATS/CATS.pdf
Got to page no 108,173.
Regards
Nitin
Edited by: Nitin Patoliya on Nov 27, 2008 12:50 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
U can check in CJI3 report for WBS, Activities.
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.