Hi Gurus

We have imported the client transport from Production to QA. Completed SCC7 post processing.

We have verified that all the RFC destinations, partner profiles, ports, logical system names are pointing to all QA systems only. User master data is reimported back to QA.

Is there anything we might have missed which can lead to exploitation of production system?

Our client is sensitive about production data, hence, the requirment to safeguard this process.

Any clues?

Thanks in advance,

Abdul

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI Abdul

Here are few things that i can think right now ,, some of you might have completed as well ..

Run SGEN

Check SAP standard jobs are running or not ,,

adjust logon groups and operation modes

schedule backup and runstats, reorgchk, dbastatc

configure STMS

check temse inconsistancy

check profile paramters , if they need to be changed

Important SAP Notes - 134777, 7317, 76517, 91976, 16875, 122222, 121163, 82029, 646393

Hope this information will help you ,, ,

cheers

dEE