on 11-25-2008 7:09 AM
Dear experts,
Is their any method to solve this issue.
Let us consider X Profit centeru2026u2026.Y Profit center.
X Profit center is using normally PS Module since startingu2026.(customer based projects) working smoothly.
Y Profit center they are using only SD Module.
Y Profit center
They use to create sale order.
Billingu2026manually
Create PO manually.
Booking also.
Now this Y Profit center they want to convert all their projects in to PS Module. for only one reason to use RA.
Now they want Y Profit center all projects should work as X Profit center.
Can u plz tell me any procedure with steps.
Regards
Chandra
why can't you set up as projects with Y profit centre?
WBS can have different profit centres
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.