Hi Experts,

Please help me!

I am integrating SD with FI-CA.

I would like to add the field cost center in the tab account assignment.

How can I do?

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

we can maintain cost center in sales order header. without any enhancement.

Goto OVF3. click on new entries, maintain sales area, order reason (E.g 102), cost center and valid from .

Now goto VA01, enter sold-to party, material and other information.

Select the value in order reason field (E.g 102).

Now goto header details account assignment tab, you find the cost center field.

Regards,

Chandra

Former Member
0 Kudos

Dear Chandra,

Thanks for the valuable information.

Is there any other settings need to be done, as I've just tested, Step-by-Step, but I've not found Field: Cost Center in to my Sales Order (VA01) --> Tab: Account Assignment (Header)?

Very Best Regards,

Amit

Former Member
0 Kudos

Hi Amit,

I don't think any other settings, Just I maintained entries in OVF3.

E.g sales area order reason cost center valid from

A001 10 10 007 Fast delivery 1000 11/25/2008

I entered sold-to party, material and selected order reason 007 in over view screen.

In header details > account assignment field I got cost center 1000.

If I get anything across to me let you know.

Regards,

Chandra

Former Member
0 Kudos

Dear Chandra,

I tried, but don't know why, nothing happened - couldn't found the Cost Center in S.O.

Very Best Regards,

Amit

former_member315051
Active Contributor
0 Kudos

Dear Amit,

I have done the same thing as chandra said , its working fine , i can able to see the cost center field at header lever , please check in Header account assignment tab, i think you might have seen item level.

Regards

Ramesh

Former Member
0 Kudos

Hi,

I want maintain cost center in sales order each item.

Please help me!

Thank.

Former Member
0 Kudos

Dear Ramesh,

Well, its great that your requirement has ful-filled (most-importantly).

Also, thanks to Mr. Chandra, for sharing his knowledge on to the same.

But, in my case, I think its my hard-luck.

Best Regards,

Amit

Former Member
0 Kudos

Hi Amit,

Have you checked the settings in OKB9 wherein you assing company code to cost elements & cost centre... that might be missing in your case..

Just a thought ha...

Hrishi

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear,

Just trying to understand your requirement -

Do you want to add a "new field", named "Cost Center"; at transaction VA01 under Tab: Account Assignment (at Item Level) under?

Is this your requirement?

Best Regards,

Amit

Note: You may add a New Field - Cost Center, under Tab: Additional Data A/ Aditional Data B.

For More, refer to my posts in thread:

[Add New Field to Screen|]