Budgets by Month in Project System.

Former Member
0 Kudos

Is there a way to do budgets by month in PS? If yes, please let me know. Also can you plan by month on a WBS without using cost elements? Like in CJ40?

Thanks in advance for your help.

Eduard

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

No.you cannot do month wise Budgeting like we do in CJ40 planning.

but after budgeting you can go in Transaction CJI8 and see the budget values for a particular date.

Rgds,

Nitin

Former Member
0 Kudos

the answer is no....

budget can be released anually or as an overall....

Former Member
0 Kudos

hi,

i believe answer is no, you can't plan by period similar to CJ40. (but if later you discover how, please tell me).

however, a workaround is to use CJR2.

you can create a planning form with 12-month layout in columns so its easy to plan by period for each WBS.

you still need cost element but you may create/use just a single cost element for this purpose only.

the important thing is you have a means of easily planning per period (by column) -unlike the default CJR2 form where in you have to constantly change screens.

for a guide on creating planning form with period layout see this blog by Mr. Sreenivas Kadiam

https://www.sdn.sap.com/irj/scn/wiki?path=/display/plm/projectSystem-ExcelbasedCostPlanning