Hi PS Gurus

For e.g. if a Network Activity has an Earliest Start date of August 1 time 0:00

then in CN49N report the Earliest Start Date of the Relationship of that activity indicates July 31, at 24:00 (i.e. midnight, just a different form).

It appears a little misleading and confusing since it is in a different form(although technically it is the same time).

Just wanted to know if this is standard or is there a note so that both the dates match in terms of date and time as well.

thanks Amit

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello Amit,

Have you also checked the early dates in CNS41, because in ECC_6.0 the dates in Project Builder (CJ20N) appears same.

May be you can go thru these notes and see if at all it helps

700875

1122073

But, since the dates happen to be technically correct we need to worry about it.

Thanks & Regards,

Anish

virendra_pal
Active Contributor
0 Kudos

for FS relationship it will always be 24:00

if you have FF then you may get 00:00

you can try and check