cancel
Showing results for 
Search instead for 
Did you mean: 

Plant Turnaround - SNP

Former Member
0 Kudos

Hi!

One of our production lines is going to be maintained in December, but we'll still going to deliver the quantities promised and plan the independent requirements... My question is how to set SNP to not consider production in December, although the independent requeriments and sales orders should be considerd and planned.

Thanks and best regards,

Daniel Paiva

Gerdau IT Supply Chain.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Visu!

Even though the question was very confused and ambiguous, the answer hit the bull´s eye.

Thanks very much!

Daniel Paiva

Gerdau IT Supply Chain

Former Member
0 Kudos

Hi Daniel,

Your question is a little ambiguous. You are saying that one of your production lines will be down in december and so you don't want SNP to plan on that line.You can do this by maintaining the down time in resource or setting your ed date in material master production version(MRP4) to end before december and deactivate your PPM in APO so that the planned orders are not created on that line.

But at the same time you are saying that "although the independent requeriments and sales orders should be considerd and planned."

I am understanding this as the system should still plan on other lines.

If you don't have active PPM, the system does not create the orders on that line. have the other PPMs active.