Differnce between periodic and Resourse billing.

Former Member
0 Kudos

Differnce between periodic and Resourse billing, and how to do it in sap?..

Can anyone suggest me step wise

Thanks in advance

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Periodic billing is used when you want to bill the customer at different points of time based on the periodicity or progress of the work. Milestone billing can be used for this type of billing purposes when you want to have billing control from the project.

Resource billing is based on the resource consumption for the particular activities. Dynamic Item Processor (DIP) profile is used for the resource related billing.

Further information acn be had from the link

[http://help.sap.com/saphelp_47x200/helpdata/en/aa/96853478616434e10000009b38f83b/frameset.htm]

Hope this is of some help

Venu

Former Member
0 Kudos

how can i use the periodic biilling? i have a good idea of milestone billing ..............

wht r the steps to be followed......for periodic billing .............

need the steps and procedures ....

Former Member
0 Kudos

You can define your 'Billing Plan' in PS.

Go to the WBS element overview in WBS maintenance.

Select the relevant WBS element and choose Details --> Billing plan.

.

You may also refer the following link for better clarity

Former Member
0 Kudos

Further to my earlier explanatio

The link is given below

[http://help.sap.com/saphelp_47x200/helpdata/en/aa/96853478616434e10000009b38f83b/frameset.htm]

Venu