Rem.Order plan in Assigned values

Former Member
0 Kudos

When I plan a service activity, the cost plan in that activity also is flowing to Assigned values,though No PR has been generated for that service activity,bcoz of this I am not able to release partial budget.As per my understanding the Rem.Order Plan also flows to assigned values.whereas in the in the case of materials,though i plan the material costs,only after generating the PR the values flow to assigned values.Can the same facility be set for Service activity also???

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

THANKS

Former Member
0 Kudos

THANKS

SOLVED THRU OPSV