on 11-21-2008 4:51 PM
We've opened a ticket with SAP; in the meantime we're looking for peer help in an SCM dilemma.
(CVC = Characteristic Value Combination)
System is Unicoded; version: SCM 4.1
Sftw Comp | Release | Level | Highest Support | Description |
SAP_ABA | 640 | 0020 | SAPKA64020 | Cross-Application Component |
SAP_BASIS | 640 | 0020 | SAPKB64020 | SAP Basis Component |
PI_BASIS | 2006_1_640 | 0004 | SAPKIPYL04 | Basis Plug-In (PI_BASIS) 2006_1_640 |
ST-PI | 2005_1_640 | 0008 | SAPKITLQH8 | SAP Solution Tools Plug-In |
SAP_BW | 350 | 0020 | SAPKW35020 | SAP_BW 350 |
SCM | 410 | 0016 | SAPKY41016 | Supply Chain Management 4.1 |
SCM_BASIS | 410 | 0016 | SAPK-41016INSCMBASIS | SCM Basis 4.1: installation |
We are seeing longer run for jobs that create CVCs, copy CVCs and backup cubes).
Program: /SAPAPO/RMQUOT_PAREA_CR
The volumes are affecting planning book loads due to CVC create finishing close to the beginning of the business day.
The root cause is that we have too many CVCs, but are stymied reducing the number.
The symptoms include:
We saw memory allocation errors (TSV) and have increased these parameters.
We try to delete unused CVCs and get the message number /SAPAPO/ATP290.
System log errors:
01:25:56 SCT_02 ENQ 000 SAPSYS GEG Lock table overflow
01:25:56 SCT_02 ENQ 000 SAPSYS GEA Internal lock administration error
01:25:56 SCT_02 ENQ 000 SAPSYS GZZ > EqSetCluster(); rtc=16 enxxmenq1905
01:25:56 SCT_02 ENQ 000 SAPSYS GEG Lock table overflow
01:25:56 SCT_02 ENQ 000 SAPSYS GEA Internal lock administration error
01:25:56 SCT_02 ENQ 000 SAPSYS GZZ > EqSetCluster(); rtc=16 enxxmenq1905
01:26:02 SCT_02 ENQ 000 SAPSYS GEG Lock table overflow
01:26:02 SCT_02 ENQ 000 SAPSYS GEA Internal lock administration error
01:26:02 SCT_02 ENQ 000 SAPSYS GZZ > EqSetCluster(); rtc=16 enxxmenq1905
01:26:02 SCT_02 ENQ 000 SAPSYS GEG Lock table overflow
01:26:02 SCT_02 ENQ 000 SAPSYS GEA Internal lock administration error
01:26:02 SCT_02 ENQ 000 SAPSYS GZZ > EqSetCluster(); rtc=16 enxxmenq1905
Current situation: only able to delete 100 CVC at a time
Anyone seen this before? Thanks!
Jim,
I'm receiving the same errors. Did you find a solution for this problem?
Lee
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
OK, we have an answer in a pilot SAP note.
Here's what support said:
please make sure that note [967889|https://service.sap.com/sap/support/notes/967889] is in your system and afterwards implment the pilote note [1082717|https://service.sap.com/sap/support/notes/1082717]. You were added as pilote customer. After implementation please check the system behaviour again and if the problem still exists send this message back to me.
Your mileage may vary, don't take wooden nickels, etc.
[Jim|https://wiki.sdn.sap.com/wiki/display/profile/Jim+Spath]
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.