I had planned for a cost for an internal activity using work center and activity type. The cost is getting displayed on planning board. Later i released that activity alone and confirmed it 100 %.
But when i see the report S_ALR_87013533, i can see only the planned cost. Actual cost is showing zero value. I also tried by releasing the WBS containing that activity, but no use.
Please advice on this issue.
Thanks,
Kabir
is the activity after conformation, is the status shown as conf (conformed)?????
r u saving the date and then checking the report?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check if this is coused by unsuficient budget, check your asigned budget and if Availability Check is activated.
You can confirm activities even if you don't have budget and the AVAC activated, in this case SAP will not transfer costs to the proyect until you assign more budget.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Did u maintained Activity type...if it is then check the price maintained in activity type for current year.
Regards
Abhinay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Abhinay,
Thanks for the reply. Yes, i have maintained the activity type for the current year. Also, i tried confirming a new Cost Activity today. But even that cost is not getting posted as actual in the report. Am able to see all planned cost values for the activities.
I checked on the Costing parameters of Network. Costingvariant plan is set to PS02 and Costingvariant Actual is set to PS03. I don't know where exactly is the issue
Please advise.
Regards,
Kabir