Dear Gurus,
The scenario is like this ---
Under the project definition, I have header level WBS element WBS 1 under which netwrok (N1) is formed.
WBS 1.1 and WBS 1.2 are under WBS 1.
Activities A1 and A2 are under WBS 1.1 and 1.2 respectively but under network (N1) which is under WBS 1.
Material M1 and M2 are attached to activities A1 and A2 respectively.
When I do advance procurement, PR are raised automatically for M1 and M2 after saving a project. But account assignment shows WBS 1.
Actually I want account assignment WBS 1.1 for M1 and WBS 1.2 for M2 as these materials are under those WBS elements and falls under the scope of its work.
Pl suggest me the necessary settings for project, WBS elements, activities and material.
Your reply will help me a lot
Thanks in advance
I think "Automatic requirement grouping" is activated in ur project. U can check the same by going to "Control Data" tab of Project Definition. See "Automatic Requirement grouping" is ticketed.
At WBS 1 it would have mentioned as gouping WBS. Same can be checked in "Basis data" tab of WBS element.
I think once PR is generated u can not undo these setting. try by deleting the PR and if u could reset.
U have to uncheck "Automatic requirement grouping" in Project Profile. From next new project this setting will apply
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.