on 11-20-2008 2:50 PM
Hi guys,
I created a new plant(PT01) which is same as an existing old plant(140H). now when i goto tcode cn22 and enter a network number and then go inside it and select the activity overview button, i get the activities. if i select one activity and click on the component overview button below the table, i cn inthe next screen assign networks to activity.
Hereif i give a material number and my old plant say 140H, and press enter i get a screen with 5 option buttons, but when i enter the same material number againt the newly created plant PT01 (whic is same like 140H), i only get 4 option buttons. can any1 tell me wat is missing intheconfig and how do i correct it????
Remeber both the plants have same config??????
Regards
Sabahuddin Ahmed
hi..
could you kindly specify what are these 5 input options and 4 input options you are saying?
is it selection for type of procurement?
anyway i really dont know yet but its possible material has not been properly extended to the other plant..
check mm02 for the material and look in MRP4 tab and COMPARE if extension to both plants have same value in field Individual/coll
revert if something else..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.