Can Anybody tell me the use of dynamic modification rule in QM .

How does it works with t-codes.

Regards,

Abhay Kale

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can use a dynamic modification rule in one of the following places:

In the inspection plan at the header level

In the inspection plan at the characteristic level

In the inspection setup of the material master record at the inspection type level DMR at lot level

A dynamic modification rule contains the definition of the inspection stages, the dynamic modification time, and the conditions that lead to an inspection stage change.

Procedure for Creation of DMR (At lot level - to check every 10th lot)

1. Execute QDR1--> Enter Modification Rule ( Eg: "tst") --> Enter Description ( eg : 'Every tenth lot to be checked') --> Select radio button at lot creation --> Click on next --> Enter stage 10 and inspection Severity as 004 > click on check box Initial Inspection Stage> Maintain short description ( eg : 'Inspect 1 st lot') --> Enter stage 20 --> click on check box skip --> Maintain short description ( eg : 'skip 9 lots') --> Press Enter and select stage 10 and click on stage change --> Enter no. of Inspections 1, New inspection stage 20 under O.K condition --> Enter no. of rejections 1, New inspection stage 20 under Not O.K condition --> Press Enter and select stage 20 and click on stage change --> Enter no. of Skips 9, New inspection stage 10 under O.K condition --> Enter no. of rejections 1, New inspection stage 10 under Not O.K condition. > Press Enter and save.> Assign dynamic modification rule to sampling procedure ( with sampling scheme). --> Save it.

2. Execute QP02 --> In header Select dynamic modification at lot level and assign dynamic modification rule ' tst' and save it.

For Automatic UD of Skip lots, Do the following settings

1. Execute mm02 -->Select Automatic UD for inspection type in material master along with Skips allowed.

2. In customization (SPRO-->Quality management --> Basic settings --> Maintain settings at plant level), Maintain Delay time for skip lot in minutes, under Insp lot completion tab for the respective plant.

Go through the below given SAP help documentation for field.

Waiting Time (Minutes) Since Insp. Lot Creation for Skip Lot

Use

Before the system can make an automatic usage decision for inspection lots with skip status, the delay time (in minutes) must have already expired since the lot was created.

Dependencies

You must allow skips in the inspection setup for the material, so that the system can modify the inspection scope dynamically to a skip stage (assuming a corresponding quality level exists).

If you activated the indicator for an automatic usage decision for goods receipt inspections in the inspection setup for the material and the inspection lot has the status skip lot, the system posts the lot quantity directly to unrestricted-use stock (ship-to stock). This occurs even if the inspection stock indicator is set in the inspection setup for the material.

or

Do manual UD In QA16 collectively for Skip lots

In the similar manner you can use Dynamic modification rule at Inspection type level and Inspection characteristic level also.

Regards,

Venkat. V

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear friend,

QDR1 is T code .

refer the following linl for dynamic modifiation rule

http://help.sap.com/printdocu/core/Print46c/en/data/pdf/QMQCDYN/QMQCDYN.pdf

sree