on 11-20-2008 12:58 PM
Dear All,
While Reducing release from WBS element by some Amount, I am getting error
as "Item WBS Element bugdet exceeded" message No: BP604
detail: Butget for fiscal year 2007 was exceeded
Regards
Honyal
solved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
Can u tell me, are u changing (reducing) the value manually in CJ32.
Regards
Chandra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Hemanth/Chandra,
my example is like this:
Release Distrublutable Assigned
overall 45,000,000.00 Rs 45,000,000.00 0.00
2007 44,754,329.57 Rs 44,754,329.57 44,754,329.57
2008 245,670.43 Rs 245,670.43 7,245,141.40-
For 2008 assigned is in Negative 7,245,141.40
while going to reduce the released budget of an WBS element
it is giving error as: In doc item WBS element ABC, budget for fiscal year 2007 was exceeded by 6,000,000 Rs
Regards
Honyal
Hi
Check your available "released" budget in CJ31. Your availabilty control is active on released budget amount. It is exceeding the tolerance limit.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.