Progress tracking

Former Member
0 Kudos

Hello all,

What is the use of progress tracking. In PS SPRO i can see there are separate configuration required for progress analysis and progress tracking. What is the difference.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

propgress analysis is the earned value analysis using measurement method

progress tracking is tracking the progress of the component (material) e.g. if you buy a critical equpment for your project you can monitor various tasks for the activity like writing specs, design, inspection etc - it is effectively micro-management of a PO similar functionlity of dscheduling as networks

- it used to be called monitoring of dates and from ECC it is called progress tracking

Answers (1)

Answers (1)

Former Member
0 Kudos

Progress Tracking:

Progress Tracking is to monitor the Procurement Process. In customization u define events (ex: Quotation. PR, PO) and link them in a sequence to create event scenario. U need define the Progress tracking profile how the variance to be shown in the report. When u run schedule base line date established and u can check the variance with respect to actual dates.

http://help.sap.com/saphelp_47x200/helpdata/en/72/8bfc048f963d4b8185ae1c0795d57b/frameset.htm

Progress Analysis:

It is to monitor the Project Progress in terms of Cost and Time. It is evaluated with the help of earned values.

http://help.sap.com/saphelp_47x200/helpdata/en/b4/ba853488601e33e10000009b38f83b/frameset.htm

Venkat