SNP PDS priority when running SNP Heuristics

Former Member
0 Kudos

Hi all,

I'm currently working with SCM 5.0 and I would like to know if it is possible to set priorities on the SNP PDS so when the SNP Heuristics is executed it selects the SNP PDS with highest priority.

I've set procurement priorities in the SNP PDSs but Heuristics seems not to take them into account

Thanks in advance

Lorea

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

I just realised Heuristics does have into account the PDS priority. In the case of multiple PDS , if all have suitable lot size, the SNP Heuristics will choose the PDS with highest Procurement Priority