Hi experts,

I have a doubt concerning SRM integration in backend system (R/3). Is it possible to change PO data (for example cost center) while integrating with r/3 (for example with a badi).

Looking forward to hear from you,

Best Regards,

Mário.

Accepted Solutions (1)

Accepted Solutions (1)

imthiaz_ahmed
Active Contributor
0 Kudos

Yes you can. Check this BADI BBP_CREATE_BE_PO_NEW (SRM 5.0) or BBP_CREATE_PO_BACK

Regards, IA