Hi

I have a unique requirement

I want the delivery date calculated in the sales order based on the following

we have products that have delivery date as 1 or 2 days

and we need one day for the wm to pick pack and load

we have used route determination.

so when a sales order will be created after ATP check the material avaialbility date will be determined and if the date is current then a delivery will be created which will be sent to wms

now for this delivery date calculation

i want is tht if the ship date falls on a thursday am then the system should be able to change the 2 day day route to 1 day (change the route ) i.e make it overnight

or change the shipping date to monday

in short we dont want the transit time to contain any weekends

i.e the goods should be received in one day or 2 day and we cant have a weekend in between for the transit times

can any one suggest how can this be achieved.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member536836
Active Contributor
0 Kudos

Hi,

I feel this is purely shipping customisation which will take care. Please go through the link in SPRO

LE-Shipping -Basic shipping functions-Scheduling -Maintain duration

Hope this input helps you to meet your requirement.