Dear Friends,
I am a BI Consultant implementing BI Reports for cProjects. I am facing problem in Planned/Latest Start date and Planned/Latest End Date for a TASK which is overwritten by Actual Start Date and Actual End Date.
I have checked the extractors in source system, the data is matching with the source system.
When I checked the table - CGPL_TASK, Planned Start Date, Latest Start Date and Actual Start Date are same. In the same manner Planned End Date, Latest End Date, and Actual End Date are same.
Please provide some inputs where I can get the correct data for Planned/Latest Start Date & Planned/Latest End Date.
Points will be awarded...
Regards,
Geeta
hi,
can u please eloborate more on this.
- r u facing this problem in cproject front end.
- or u want source of correct data for evaluation purpose.
Regards,
Pramod
plz award pts if its useful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pramod,
I am facing the problem in Front End as well as in CRM Source System.
I checked the CGPL_TASK table without giving any Actual dates for the task as well as with Actual Dates. When the Actual Dates are updated in the frontend , The dates for Planned and Latest get overwritten in source as well as in front end.
Regards,
Geeta
User | Count |
---|---|
9 | |
7 | |
3 | |
2 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.